Assume the bigd daemon fails on the active system. Which three are possible results? (Choose three.)
A.
The active system will restart the bigd daemon and continue in active mode.
B.
The active system will restart the tmm daemon and continue in active mode.
C.
The active system will reboot and the standby system will go into active mode.
D.
The active system will failover and the standby system will go into active mode.
E.
The active system will continue in active mode but gather member and node state information from the standby system.