Which of the following should an information security manager do NEXT after creating a roadmap to execute the strategy for an information security program?
A.
Obtain consensus on the strategy from the executive board.
B.
Review alignment with business goals.
C.
Define organizational risk tolerance.
D.
Develop a project plan to implement the strategy.
Your answer: