You are creating a build pipeline in Azure Pipelines.

You define several tests that might fail due to third-party applications.

You need to ensure that the build pipeline completes successfully if the third-party applications are unavailable. What should you do?

A.
Configure the build pipeline to use parallel jobs
Answers
A.
Configure the build pipeline to use parallel jobs
B.
Configure flaky tests
Answers
B.
Configure flaky tests
C.
Increase the test pass percentage
Answers
C.
Increase the test pass percentage
D.
Add the Requirements quality widget to your dashboard
Answers
D.
Add the Requirements quality widget to your dashboard
Suggested answer: D

Explanation:

Requirements traceability is the ability to relate and document two or more phases of a development process, which can then be traced both forward or backward from its origin. Requirements traceability help teams to get insights into indicators such as quality of requirements or readiness to ship the requirement. A fundamental aspect of requirements traceability is association of the requirements to test cases, bugs and code changes.

Reference:

https://docs.microsoft.com/en-us/azure/devops/pipelines/test/requirements-traceability