Refer to the exhibit.


An administrator is tasked with adding new capacity to an existing software-defined data center (SDDC).

• The SDDC currently hosts two vSphere clusters (ClusterA and ClusterB) with different CPU compatibilities.

• vSphere vMotion and vSphere Distributed Resource Scheduler (DRS) are currently in use in the

SDDC.

• The new capacity will be implemented by provisioning four ESXi hosts running a new generation of Intel Skylake CPUs.

• All workload virtual machines (VMs) must support live migration to any cluster in the SDDC.

The administrator noticed the running critical "ever virtual machine (VM) shown in the exhibit is not migrating using vSphere vMotion to the original Clusters A or B.

Which three steps must the administrator take to support this functionality? (Choose three.)

A.
Power on the VM.
Answers
A.
Power on the VM.
B.
Disable the Enhanced vMotion Compatibility (EVC) on the VM.
Answers
B.
Disable the Enhanced vMotion Compatibility (EVC) on the VM.
C.
Reboot the VM.
Answers
C.
Reboot the VM.
D.
Configure the Enhanced vMotion Compatibility (EVC) on vSphere Cluster A and B to support IntelSkylake.
Answers
D.
Configure the Enhanced vMotion Compatibility (EVC) on vSphere Cluster A and B to support IntelSkylake.
E.
Power off the VM.
Answers
E.
Power off the VM.
F.
Configure the Enhanced vMotion Compatibility (EVC) on the VM to Intel Skylake.
Answers
F.
Configure the Enhanced vMotion Compatibility (EVC) on the VM to Intel Skylake.
Suggested answer: A, D, E