Question 127 - CLO-002 discussion
A company is planning to use cloud computing to extend the compute resources that will run a new resource-intensive application. A direct deployment to the cloud would cause unexpected billing. Which of the following must be generated while the application is running on-premises to predict the cloud budget for this project better?
A.
Proof or concept
B.
Benchmark
C.
Baseline
D.
Feasibility study