Question 286 - CS0-003 discussion
An organization has established a formal change management process after experiencing several critical system failures over the past year. Which of the following are key factors that the change management process will include in order to reduce the impact of system failures? (Select two).
A.
Ensure users the document system recovery plan prior to deployment.
B.
Perform a full system-level backup following the change.
C.
Leverage an audit tool to identify changes that are being made.
D.
Identify assets with dependence that could be impacted by the change.
E.
Require diagrams to be completed for all critical systems.
F.
Ensure that all assets are properly listed in the inventory management system.