An engineer notices some late collisions on a half-duplex link. The engineer verifies that the devices on both ends of the connection are configured for half duplex. Which of the following is the MOST likely cause of this issue?
A.
The link is improperly terminated
B.
One of the devices is misconfigured
C.
The cable length is excessive
D.
One of the devices has a hardware issue