A systems engineer is building a new system for production. Which of the following is the FINAL step to be performed prior to promoting to production?

A.
Disable unneeded services.
Answers
A.
Disable unneeded services.
B.
Install the latest security patches.
Answers
B.
Install the latest security patches.
C.
Run a vulnerability scan.
Answers
C.
Run a vulnerability scan.
D.
Encrypt all disks.
Answers
D.
Encrypt all disks.
Suggested answer: C

Explanation:

Running a vulnerability scan is the final step to be performed prior to promoting a system to production. This allows any remaining security issues to be identified and resolved before the system is put into production. Reference: CompTIA Security+ Study Guide, Exam SY0-601, 4th Edition, Chapter 3