A systems administrator would like to deploy a change to a production system. Which of the following must the administrator submit to demonstrate that the system can be restored to a working state in the event of a performance issue?

A.
Backout plan
Answers
A.
Backout plan
B.
Impact analysis
Answers
B.
Impact analysis
C.
Test procedure
Answers
C.
Test procedure
D.
Approval procedure
Answers
D.
Approval procedure
Suggested answer: A

Explanation:

To demonstrate that the system can be restored to a working state in the event of a performance issue after deploying a change, the systems administrator must submit a backout plan. A backout plan outlines the steps to revert the system to its previous state if the new deployment causes problems.

Backout plan: Provides detailed steps to revert changes and restore the system to its previous state in case of issues, ensuring minimal disruption and quick recovery.

Impact analysis: Evaluates the potential effects of a change but does not provide steps to revert changes.

Test procedure: Details the steps for testing the change but does not address restoring the system to a previous state.

Approval procedure: Involves obtaining permissions for the change but does not ensure system recovery in case of issues.