Which of the following describes effective change management procedures?

A.
Approving the change after a successful deployment
Answers
A.
Approving the change after a successful deployment
B.
Having a backout plan when a patch fails
Answers
B.
Having a backout plan when a patch fails
C.
Using a spreadsheet for tracking changes
Answers
C.
Using a spreadsheet for tracking changes
D.
Using an automatic change control bypass for security updates
Answers
D.
Using an automatic change control bypass for security updates
Suggested answer: B

Explanation:

Effective change management procedures include having a backout plan when a patch fails. A backout plan ensures that there are predefined steps to revert the system to its previous state if the new change or patch causes issues, thereby minimizing downtime and mitigating potential negative impacts.

Having a backout plan when a patch fails: Essential for ensuring that changes can be safely reverted in case of problems, maintaining system stability and availability.

Approving the change after a successful deployment: Changes should be approved before deployment, not after.

Using a spreadsheet for tracking changes: While useful for documentation, it is not a comprehensive change management procedure.

Using an automatic change control bypass for security updates: Bypassing change control can lead to unapproved and potentially disruptive changes.