As part of a new hybrid cloud initiative for a large financial company, the customer technical team is presenting an overview of the current state of the infrastructure and their vision for a new solution.

The project team captures notes during the presentation and adds them to the discovery documentation. Which of the listed statements is a design constraint?

A.
The applications are created in-house with in-guest recovery protection
Answers
A.
The applications are created in-house with in-guest recovery protection
B.
The maximum tolerable data loss is 10 minutes
Answers
B.
The maximum tolerable data loss is 10 minutes
C.
The two data center locations have a network latency of 8 ms round-trip time (RTT)
Answers
C.
The two data center locations have a network latency of 8 ms round-trip time (RTT)
D.
The existing storage is out of maintenance
Answers
D.
The existing storage is out of maintenance
Suggested answer: C

Explanation:

Networking Requirements for vSAN Maximum of 1 ms RTT for standard (non-stretched) vSAN clusters between all hosts in the cluster Maximum of 5 ms RTT between the two main sites for stretched clusters Maximum of 200 ms RTT from a main site to the vSAN witness host https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan-planning.doc/GUID- AFF133BC-F4B6-4753-815F-20D3D752D898.html