A company hosts a vSAN 7 stretched cluster for all development workloads. The original sizing of a maximum of 250 concurrent workloads in the vSAN cluster is no longer sufficient and needs to increase to at least 500 concurrent workloads within the next six months.

To meet this demand, the original 8-node (4-4-1) cluster has recently been expanded to 16 nodes (8-8-1).

Which three additional steps should the administrator take to support the current growth plans while minimizing the amount of resources required at the witness site? (Choose three.)

A.
Add the new vSAN witness appliance to vCenter Server.
Answers
A.
Add the new vSAN witness appliance to vCenter Server.
B.
Deploy a new large vSAN witness appliance at the witness site.
Answers
B.
Deploy a new large vSAN witness appliance at the witness site.
C.
Configure the vSAN stretched cluster to use the new vSAN witness.
Answers
C.
Configure the vSAN stretched cluster to use the new vSAN witness.
D.
Deploy a new extra large vSAN witness appliance at the witness site.
Answers
D.
Deploy a new extra large vSAN witness appliance at the witness site.
E.
Upgrade the vSAN stretched cluster to vSAN 7.0 U1.
Answers
E.
Upgrade the vSAN stretched cluster to vSAN 7.0 U1.
F.
Configure the new vSAN witness as a shared witness appliance.
Answers
F.
Configure the new vSAN witness as a shared witness appliance.
Suggested answer: A, B, C

Explanation:

https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan-planning.doc/GUID-05C1737A-5FBA-4AEE-BDB8-3BF5DE569E0A.html