A fitness company has several locations.

The company implements Dynamics 365 Customer Service and uses it to schedule personal trainer sessions with customers.

Customers report the following issues:

Customers are assigned personal trainers who do not reside at the customer's location.

Customers are assigned personal trainers during the trainers' non-working hours.

You need to resolve the issues.

Which two settings should you configure? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

A.

Customer Service Calendar

Answers
A.

Customer Service Calendar

B.

resource skills

Answers
B.

resource skills

C.

Work Hours

Answers
C.

Work Hours

D.

facility resources

Answers
D.

facility resources

E.

Fulfillment Preferences

Answers
E.

Fulfillment Preferences

Suggested answer: A, C

Explanation:

Reference:

https://docs.microsoft.com/en-us/dynamics365/customer-service/resources-service-scheduling