List of questions
Related questions
Question 54 - 5V0-22.21 discussion
An administrator has successfully deployed a new 3-node vSAN Cluster. Prior to deploying any production workloads on to the new cluster, the administrator must complete a number of Service Validation and Testing (SVT) checks.
The final check requires the administrator to pull out a disk from one of the vSAN hosts.
Which two outcomes will occur within the vSAN cluster following this action? (Choose two.)
A.
By default. vSAN will delay the rebuilding of affected components for 60 minutes.
B.
All components on the device will be marked as absent.
C.
By default. vSAN will start the rebuilding of affected components immediately.
D.
By default vSAN will delay the rebuilding of affected components for 30 minutes.
E.
All components on the device will be marked as degraded.
Your answer:
0 comments
Sorted by
Leave a comment first