A vSAN administrator is deploying a four node vSAN cluster to a new work location. To help with configuration and consistency, the vSAN administrator plans to use Ouickstart Which two prerequisites must be met prior to taking this action? (Choose two.)
A.
vDS must be created tor vSAN and management traffic.
B.
DRS and HA have been enabled.
C.
vCenter is running on one of the four nodes.
D.
Hosts are running 6.0 U2 or later.
E.
Hosts do not have existing vSAN or network configurations.