You are a functional consultant for a company named Contoso Entertainment System USA (USMF).

You need to configure a new quality process for item number M0017. The process must meet the following requirements:

Perform an impedance test on 100 percent of the units purchased.

Initiate the test after the product receipt is posted.

To complete this task, sign in to Dynamics 365 portal.

A.
Answers
A.
Suggested answer: A

Explanation:

Answer: A

Explanation:

Configure Item Sampling to specify 100 percent of the units.

Configure Quality Association to specify what test to run and configure the test to run after the receipt is posted.

Configure Item Sampling.

1. Go to Inventory management > Setup > Quality control > Item sampling.

2. Click New.

3. In the Item sampling field, type the name 100%.

4. In the Description field, type a value (100%).

5. In the Quantity specification field, select percent.

6. In the Value field, enter a number (100)

7. Click Save.

8. Close the page.

Configure a Quality Association

1. Go to Inventory management > Setup > Quality control > Quality associations.

2. Click New.

3. In the Reference type field, select Purchase.

4. In the Item code field, select Table.

5. In the Item field, select the item M0017.

6. In the Event type field, select Product Receipt.

7. In the Execution field, select After.

8. Expand or collapse the Specifications section.

9. In the Test group field, find and select the Impedance test.

10. Click Save.

11. Close the page.

Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/inventory/tasks/set-up-quality-orders

https://docs.microsoft.com/en-us/dynamics365/supply-chain/inventory/enable-quality-management

asked 05/10/2024
Aung Zin
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first