Question 227 - MB-330 discussion
A company uses the built-in Dynamics 365 Supply Chain Management master planning engine. Planned orders are automatically firming and are firmed during the current week.
You need to reconfigure the system for the new Planning Optimization master planning engine.
What should you change?
A.
firming time fence to one week
B.
firming time fence to lead-time plus one week
C.
open orders' firming date to be the requirement date
D.
firming time fence to be longer than the lead time
E.
firming time fence to 0