Question 246 - MB-330 discussion

Report
Export

A company uses Planning Optimization.

A customer calls a service agent at the company and asks about product availability dates when placing an order.

Capable to promise (CTP) is initiated from the customer's order.

What is the expected output?

Select only one answer.

A.

An error occurs because CTP is not supported when Planning Optimization is enabled.

Answers
A.

An error occurs because CTP is not supported when Planning Optimization is enabled.

B.

Built-in master planning runs the calculation if the master plan has a separate dynamic master plan specified.

Answers
B.

Built-in master planning runs the calculation if the master plan has a separate dynamic master plan specified.

C.

A warning shows in the plan history log.

Answers
C.

A warning shows in the plan history log.

D.

CTP runs if add-ins are installed from Feature management.

Answers
D.

CTP runs if add-ins are installed from Feature management.

E.

CTP calculates if all Planning Optimization jobs are withheld from batch scheduling.

Answers
E.

CTP calculates if all Planning Optimization jobs are withheld from batch scheduling.

Suggested answer: A

Explanation:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planningoptimization/planning-optimization-trouble-shooting

asked 05/10/2024
Haleem SHITOU OGUNGBEMI
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first