Question 252 - MB-330 discussion

Report
Export

A company uses Planning Optimization.

You need to ensure that the purchase price trade agreement lead time is used for an item.

What should you do?

A.

Set the days forward parameter.

Answers
A.

Set the days forward parameter.

B.

Set the Disregard lead time parameter to No.

Answers
B.

Set the Disregard lead time parameter to No.

C.

Set the Disregard lead time parameter to Yes.

Answers
C.

Set the Disregard lead time parameter to Yes.

D.

Override the item lead time parameter.

Answers
D.

Override the item lead time parameter.

E.

Set the days backward parameter.

Answers
E.

Set the days backward parameter.

Suggested answer: B