A company requires that a percentage of the building overhead costs as well as a percentage of overall labor must be added to a costing sheet for each item.
The company also requires that the labor and overhead costs be calculated independently and then rolled up to a total amount.
Which three actions should you perform to meet the requirements?
Select all answers that apply.
A.
Select Cost group type as a node.
B.
Create indirect cost subnodes.
C.
Define the costing sheet format.
D.
Define the rate amount on the node.
E.
Define the rate amount on the cost group.
Your answer: