Question 259 - MB-330 discussion
You run Planning Optimization. You create a static master plan with a plan filter for A and B items.
Purchasing agents for the A items start to review the A item output. You must re-run planning for the B items due to a change. Re-running the B items must not impact the existing planned orders for the A items.
You need to re-run planning for the B items.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
Select all answers that apply.
Re-run the static plan with the runtime filter set for the A items.
Delete the planned orders for the B items and re-run the static plan.
Run a dynamic plan with a plan filter for the B items.
Run a dynamic plan with a plan filter for the A items.
Re-run the static plan with the runtime filter set for the B items.
0 comments