You run Planning Optimization. You create a static master plan with a plan filter for A and B items.

Purchasing agents for the A items start to review the A item output. You must re-run planning for the B items due to a change. Re-running the B items must not impact the existing planned orders for the A items.

You need to re-run planning for the B items.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

Select all answers that apply.

A.

Re-run the static plan with the runtime filter set for the A items.

Answers
A.

Re-run the static plan with the runtime filter set for the A items.

B.

Delete the planned orders for the B items and re-run the static plan.

Answers
B.

Delete the planned orders for the B items and re-run the static plan.

C.

Run a dynamic plan with a plan filter for the B items.

Answers
C.

Run a dynamic plan with a plan filter for the B items.

D.

Run a dynamic plan with a plan filter for the A items.

Answers
D.

Run a dynamic plan with a plan filter for the A items.

E.

Re-run the static plan with the runtime filter set for the B items.

Answers
E.

Re-run the static plan with the runtime filter set for the B items.

Suggested answer: C, D