A company uses planning optimization in Dynamics 365 Supply Chain Management A new item is set up for production with a bill of materials (BON') and is included in planning optimization.

You need to identify the planning output for the item

What are two parts of the output? Each answer represents a partial solution

A.

production order

Answers
A.

production order

B.

action message

Answers
B.

action message

C.

purchase order

Answers
C.

purchase order

D.

Warning

Answers
D.

Warning

Suggested answer: B, C

Explanation:

Action messages are generated by the master planning calculation in response to changed requirements. For example, the ship date or quantity is changed on a sales order after you've already created a purchase order to fulfill the demand for that sales order. In this case, the master planning calculation generates one or more action messages that suggest that you update the purchase order.

You decide whether to make the changes that are suggested.

Actions that are related to components of bills of material (BOMs) must be applied before the actions of their parent items, because further orders that are related to higher-level BOMs might be affected.

Reference: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/actionmessages

asked 05/10/2024
Najim Abdelmoula
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first