You need to plan scheduling for Customer1's order of unscented solution.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

A.

Schedule production based on the availability of raw material.

Answers
A.

Schedule production based on the availability of raw material.

B.

Split and plan operations in detail for each of the resources.

Answers
B.

Split and plan operations in detail for each of the resources.

C.

Schedule productions based on the capacity of the resources.

Answers
C.

Schedule productions based on the capacity of the resources.

D.

Run master planning with a specific time fence.

Answers
D.

Run master planning with a specific time fence.

E.

Plan scheduling of the production at the resource group level.

Answers
E.

Plan scheduling of the production at the resource group level.

Suggested answer: C, E