Question 74 - PL-500 discussion
You are creating a cloud flow that will use two Update Row actions to interact with Microsoft Dataverse. Neither of these actions are dependent on each other. You must minimize the amount of processing time required to complete the flow. You need to implement the actions in the cloud flow.
Solution: Create two sequential Update Row actions.
Does the solution meet the goal?
A.
Yes
B.
No