Question 76 - 300-425 discussion
An engineer changed the TPC Power Threshold for a wireless deployment from the default value to -65 dBm. The engineer conducts a new post-deployment Survey to validate the results. What is the expected outcome?
A.
Increase cell size
B.
Decreased client signal strength
C.
Increased received sensitivity
D.
Decreased channel overlap
Your answer: