An engineer changed the TPC Power Threshold for a wireless deployment from the default value to -65 dBm. The engineer conducts a new post-deployment Survey to validate the results. What is the expected outcome?

A.

Increase cell size

Answers
A.

Increase cell size

B.

Decreased client signal strength

Answers
B.

Decreased client signal strength

C.

Increased received sensitivity

Answers
C.

Increased received sensitivity

D.

Decreased channel overlap

Answers
D.

Decreased channel overlap

Suggested answer: A