Based on a wireless network design, an engineer configured a primary and secondary controller for their APs. A power interruption caused the primary Cisco WLC to go down, and, as expected, all APs joined the secondary controller. When the primary controller came back up, all the APs remained joined to the secondary controller. Which approach must the engineer take for the APs to move back to the primary?
A.
Set AP Fail over Priority to 4 on each AP.
B.
Set AP Fallback to Enabled on the secondary controller.
C.
Set AP Fallback to Enabled on the primary controller.
D.
Set AP Fail over Priority to Critical globally.