What does a work center control? Note: There are 2 correct answers to this question.

A.

Calculation of costs of work performed

Answers
A.

Calculation of costs of work performed

B.

Release of production orders

Answers
B.

Release of production orders

C.

Availability of capacity

Answers
C.

Availability of capacity

D.

Valuation of bill of material components

Answers
D.

Valuation of bill of material components