Which time elements are considered during backwards scheduling for planned orders? Note: There are 3 correct answers to this question.

A.

Goods receipt processing time

Answers
A.

Goods receipt processing time

B.

Opening period

Answers
B.

Opening period

C.

Quality inspection time

Answers
C.

Quality inspection time

D.

Goods issue processing time

Answers
D.

Goods issue processing time

E.

In-house production time

Answers
E.

In-house production time

Suggested answer: A, B, E