Question 3 - C_THR94_2405 discussion

Report
Export

Which of the following can lead to automatic absence recalculation?Note: There are 3 correct answers to this question.

A.

Changes to the Work Schedule in Job Information

Answers
A.

Changes to the Work Schedule in Job Information

B.

Changes to the Holiday Calendar in Job Information

Answers
B.

Changes to the Holiday Calendar in Job Information

C.

Changes in the Work Schedule object

Answers
C.

Changes in the Work Schedule object

D.

Changes in the Temporary Time Information object

Answers
D.

Changes in the Temporary Time Information object

E.

Changes in the Holiday Calendar object

Answers
E.

Changes in the Holiday Calendar object

Suggested answer: A, B, D