When running MRP, what setting in the material master determines if a material will be procured or produced?

A.

Procurement type

Answers
A.

Procurement type

B.

Purchasing group

Answers
B.

Purchasing group

C.

MRP type

Answers
C.

MRP type

D.

Processing key

Answers
D.

Processing key

Suggested answer: A

Explanation:

In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish the material - by generating purchase requisitions for external procurement or planned orders for in-house production. Reference = SAP Material Management (MM) and Production Planning (PP) documentation.

asked 31/10/2024
Tom Starren
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first