What function commits funds assigned to the budget of a WBS element?

A.

Availability control

Answers
A.

Availability control

B.

Cost center accounting

Answers
B.

Cost center accounting

C.

Settlement processing

Answers
C.

Settlement processing

D.

Profitability analysis

Answers
D.

Profitability analysis

Suggested answer: A

Explanation:

Availability Control (A) is the function that commits funds assigned to the budget of a WBS (Work Breakdown Structure) element. It monitors budget consumption and can issue warnings or prevent further postings when budget limits are exceeded, ensuring that project spending stays within approved budgets. Reference = SAP Project System (PS) documentation and financial controls guides.