What is the result of converting a planned order? Note: There are 2 correct answers to this question

A.

A planned independent requirement

Answers
A.

A planned independent requirement

B.

A purchase requisition

Answers
B.

A purchase requisition

C.

A purchase order

Answers
C.

A purchase order

D.

A production order

Answers
D.

A production order

Suggested answer: B, D

Explanation:

Converting a planned order can result in the creation of a Purchase Requisition (B) for externally procured materials or a Production Order (D) for in-house manufactured items. This step is crucial in the procurement and production planning process, initiating the procurement or manufacturing of required materials. Reference = SAP Material Management (MM) and Production Planning (PP) documentation.