What elements are recorded during an overall completion confirmation of a maintenance order? Note: There are 3 correct answers to this question

A.

Time entry

Answers
A.

Time entry

B.

Measuring documents

Answers
B.

Measuring documents

C.

Availability check

Answers
C.

Availability check

D.

Materials

Answers
D.

Materials

E.

Invoicing

Answers
E.

Invoicing

Suggested answer: A, B, D

Explanation:

During an overall completion confirmation of a maintenance order in SAP, the following elements are recorded:

Time entry (A): The actual time spent on the maintenance activities is recorded, providing data for labor cost calculation and productivity analysis.

Measuring documents (B): These capture measurements and readings from equipment before, during, and after maintenance, contributing to equipment history and performance analysis.

Materials (D): The materials used during the maintenance work are recorded, ensuring accurate inventory management and cost allocation.

An Availability check (C) is part of the planning and preparation for maintenance work but is not typically an element recorded during the completion confirmation.

Invoicing (E) is related to the billing process for external services and is not an element recorded during the overall completion confirmation of internal maintenance orders.