An enterprise is implementing its first mobile sales channel. Final approval for accepting the associated IT risk should be obtained from which of the following?

A.

Risk manager

Answers
A.

Risk manager

B.

Business sponsor

Answers
B.

Business sponsor

C.

Chief information officer (CIO)

Answers
C.

Chief information officer (CIO)

D.

IT steering committee

Answers
D.

IT steering committee

Suggested answer: B

Explanation:

Final approval for accepting the associated IT risk should be obtained from the business sponsor.This is because the business sponsor is the person or group who initiates, funds, and owns the business case for the mobile sales channel project1.The business sponsor is responsible for defining the business objectives, benefits, and requirements of the project, and for ensuring its alignment with the enterprise strategy1.The business sponsor is also accountable for the outcomes and value of the project, and for managing the risks and issues that may affect its success1. Therefore, the business sponsor should have the authority and responsibility to approve the IT risk associated with the mobile sales channel project, as it may impact the business performance and value.

The other options, risk manager, chief information officer (CIO), and IT steering committee are not the best choices for obtaining final approval for accepting the associated IT risk.They are more involved in the identification, assessment, mitigation, and monitoring of IT risks, rather than their acceptance2. They may also have different perspectives and interests than the business sponsor regarding the IT risk associated with the mobile sales channel project. For example, the risk manager may focus on minimizing or avoiding IT risks, while the CIO may focus on maximizing or exploiting IT opportunities. The IT steering committee may have a broader view of IT risks across multiple projects and programs, rather than a specific one. Therefore, they may not have the final say or decision on accepting the IT risk associated with the mobile sales channel project.