You want to use budget availability control for your projects and internal orders. What can you check using budget availability control?

Note: There are 2 correct answers to this question.

A.

The availability of funds in object currency

Answers
A.

The availability of funds in object currency

B.

The availability of funds on a period level

Answers
B.

The availability of funds on a period level

C.

The availability of funds using overall plan value

Answers
C.

The availability of funds using overall plan value

D.

The availability of funds according to tolerance limits

Answers
D.

The availability of funds according to tolerance limits

Suggested answer: C, D

Explanation:

Budget availability control in SAP S/4HANA allows checking funds based on overall plan value (option C) and tolerance limits (option D). These checks ensure effective budget management across projects and internal orders.