Examine the configuration of Core-1 and Core-2. AOS-CX switches configured as a VSX stack:

Core1: Interlace lag 256

no shutdown

no routing

vlan trunk allowed all

lacp mode active Interface 1/1/46

no shutdown

lag 256 Interface 1/1/47

no shutdown

lag 256

VSX

Inter-switch-link lag 256

vsx-sync vsx-global

exit

Cofe2: interlace lag 250

no shutdown

no routing

vlan trunk allowed all

lacp mode active

Interlace 1/1/46

no shutdown

lag 256 Interface 1/1/47

no shutdown

lag 256 vsx

inter-switch-link lag 256

exit

When using the 'show vsx status' command, the two switches fall to connect and successfully synchronize. What should the administrator do to fix this issue?

A.
Define a larger MTU on the ISL link of the two switches.
Answers
A.
Define a larger MTU on the ISL link of the two switches.
B.
Define the VSX roles on the two switches.
Answers
B.
Define the VSX roles on the two switches.
C.
Enable active-active forwarding on the two switches.
Answers
C.
Enable active-active forwarding on the two switches.
Suggested answer: B