Question 2 - CPIM-Part-2 discussion
A customer requests an order of 100 units in Period 1. The master schedule for the item indicates an available-to-promise
(ATP) of 85 units for Period 1. Which of the following approaches is the most appropriate course of action?
A.
Increase the master production schedule (MPS) quantity in Period 1 by 15 units.
B.
Promise the 100 units, and then check on component availability.
C.
Promise the 85 units in Period 1 and the remaining 15 units in the next possible ATP period.
D.
Promise the 100 units by removing 15 units from another customer's order with a smaller revenue value.
Your answer: