Question 139 - CPIM-Part-2 discussion

Report
Export

In the sales and operations planning (S&0P) process in a repetitive manufacturing environment, the resulting operations plan for a product family could be stated in terms of which of the following outputs?

A.
A Projected labor hours
Answers
A.
A Projected labor hours
B.
Metric tons to be produced
Answers
B.
Metric tons to be produced
C.
Value of products to be produced
Answers
C.
Value of products to be produced
D.
Number of products planned for shipment
Answers
D.
Number of products planned for shipment
Suggested answer: D

Explanation:

The sales and operations planning (S&OP) process is a cross-functional process that aligns the demand and supply plans of an organization. The S&OP process consists of several steps, such as data gathering, demand planning, supply planning, pre-S&OP meeting, executive S&OP meeting, and S&OP implementation. The output of the S&OP process is the production plan, which is a statement of the resources needed to meet the aggregate demand plan over a medium-term horizon. The production plan can be stated in different units of measure depending on the type of manufacturing environment. In a repetitive manufacturing environment, where the same or similar products are produced continuously or at regular intervals, the production plan can be stated in terms of the number of products planned for shipment. This unit of measure reflects the volume and mix of products that are expected to be sold and delivered to the customers. The number of products planned for shipment can also be used to calculate the capacity requirements, material requirements, and inventory levels for each product family.