Question 324 - CSCP discussion

Report
Export

In an advanced planning and scheduling (APS) system, which of the following processes feeds the master schedule?

A.
Purchasing planning
Answers
A.
Purchasing planning
B.
Demand planning
Answers
B.
Demand planning
C.
Distribution planning
Answers
C.
Distribution planning
D.
Fulfillment planning
Answers
D.
Fulfillment planning
Suggested answer: D

Explanation:

In an Advanced Planning and Scheduling (APS) system, the process that feeds the master schedule is fulfillment planning. This is because:

Demand Planning: Involves forecasting customer demand but does not directly feed the master schedule.

Purchasing Planning: Focuses on procuring materials and components needed for production.

Distribution Planning: Deals with the distribution of finished products to customers or other warehouses.

Fulfillment Planning: Involves coordinating the supply chain activities to fulfill customer orders efficiently and effectively, providing necessary input to create an accurate master schedule.

The master schedule requires detailed information on the availability of products and materials to meet customer orders, which is a key aspect of fulfillment planning.

'Manufacturing Planning and Control for Supply Chain Management' by F. Robert Jacobs, William L. Berry, D. Clay Whybark, and Thomas E. Vollmann

APICS Dictionary

asked 16/09/2024
Lester Ballesteros
45 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first