Question 502 - CSCP discussion
In distribution requirements planning (DRP), projected on-hand inventory is equal to the prior week's on-hand inventory minus the current week's gross requirements plus:
A.
planned production.
B.
planned orders.
C.
safety stock.
D.
scheduled receipts.
Your answer: