Question 544 - CPP discussion
The keys to the success of any emergency organization and plan are training and testing.
In designing effective testing procedures, the following are all valid observations except:
A.
Records should be maintained so deficiencies can be corrected following the test.
B.
The testing exercise should be as realistic as possible.
C.
Plenty of advance notice should be given so all possible preparations can be made.
D.
One of the best times to test the plant emergency plan is in coordination with your local government periodic test exercises.
E.
Testing of the emergency plan should require the actual operation or simulation of every element of the plan in all possible emergency conditions.