A support engineer is tasked to power down a VSP switch using the management tools available for the ACP 4200.

Which statement is true about how the engineer would accomplish this task?

A.
Login to Enterprise Device Manager and use the chassis power down option.
Answers
A.
Login to Enterprise Device Manager and use the chassis power down option.
B.
Login to Servertech PDU Web Interface and use the outlet control option.
Answers
B.
Login to Servertech PDU Web Interface and use the outlet control option.
C.
This can only be done if the engineer is on-site to switch off the VSP’s power switch.
Answers
C.
This can only be done if the engineer is on-site to switch off the VSP’s power switch.
D.
This can only be done if the engineer is on-site to remove the VSP’s power cable.
Answers
D.
This can only be done if the engineer is on-site to remove the VSP’s power cable.
Suggested answer: A