Question 42 - 76940X discussion

Report
Export

A support engineer is tasked with upgrading a CPOD 2.1 system to ACP 4200 4.0.

Which statement about the upgrade process is true?

A.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported, and a direct upgrade path is supported.
Answers
A.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported, and a direct upgrade path is supported.
B.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported only if the Rack enclosure is replaced with a new 48 Inch Deep Model.
Answers
B.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported only if the Rack enclosure is replaced with a new 48 Inch Deep Model.
C.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is not supported.
Answers
C.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is not supported.
D.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported, but a direct upgrade path is only partially supported.
Answers
D.
Upgrading a CPOD 2.1 system to ACP 4200 4.0 is supported, but a direct upgrade path is only partially supported.
Suggested answer: B