A project has been running at the Wield Engineering Company for six months. The requirements have been signed off and development is underway; however, the development team has hit a problem and cannot implement an approved requirement. The business analyst has been asked to discuss this with the requirement owner.
Before booking a meeting with the owner, the business analyst decides to check whether there are more requirements affected by this technical limitation.
What will help the business analyst discover other affected requirements?
A.
Change control
B.
Configuration control
C.
Horizontal traceability
D.
Vertical traceability