A project, which was initiated several months ago, has been impacted by the following changes:
An organizational restructure has altered the responsibilities of the stakeholders.
A new chief executive has been appointed, who has new ideas regarding the immediate focus of the project.
Which of the following attributes in a requirements catalogue entry would need to be updated to reflect these changes?
A- Owner, source.
B- Priority, owner, version history.
C- Rationale, priority, source.
D- Version history, author, rationale.
A.
A and 2
B.
A, B and 2
C.
B, C and 2
D.
B and 2