Which of the following activities can you perform in Blue Prism Control Room?
(select all items which apply)
A.
Set the Maximum Attempts parameter for the Work Queue
B.
Rename a Work Queue
C.
Delete items from a Work Queue
D.
Refresh Work Queue data
E.
Create a Work Queue
F.
Encrypt a Work Queue
Your answer: