Examine the following diagram which has been extracted from a Blue Prism Process currently being tested in Process Studio

The Request Type is a text data item and will contain a text value which categorizes the type of request being processed. The Process Request stage has been assigned a Breakpoint with the following Breakpoint condition:

What will happen if you press the Go button when debugging the Process?

A.
If the 'Request Type' value equals 'New Card', then the Process will stop at the Breakpoint on the 'Process Request' stage
Answers
A.
If the 'Request Type' value equals 'New Card', then the Process will stop at the Breakpoint on the 'Process Request' stage
B.
If the 'Request Type' value equals 'New Card' then the Process will flow to the End stage without stopping
Answers
B.
If the 'Request Type' value equals 'New Card' then the Process will flow to the End stage without stopping
C.
Breakpoints are unconditional therefore the Process flow will always stop at the 'Process Request' stage
Answers
C.
Breakpoints are unconditional therefore the Process flow will always stop at the 'Process Request' stage
D.
If the 'Request Type' value is not equal to 'New Card', then the Process will stop at the Breakpoint on the 'Process Request' stage
Answers
D.
If the 'Request Type' value is not equal to 'New Card', then the Process will stop at the Breakpoint on the 'Process Request' stage
Suggested answer: A

Explanation:

Understanding the Breakpoint:

A breakpoint in Blue Prism is used to pause the execution of a process at a specific stage, allowing for debugging.

The breakpoint can be conditional, meaning it will only pause the process if a specified condition is met.

Analyzing the Breakpoint Condition:

The provided condition is [Request Type] = 'New Card'.

This means the breakpoint on the 'Process Request' stage will only trigger if the value of the 'Request Type' data item is 'New Card'.

Possible Outcomes:

Option A: Correct. If the 'Request Type' value equals 'New Card', the process will stop at the 'Process Request' stage because the condition is met.

Option B: Incorrect. If the 'Request Type' value equals 'New Card', the process will stop at the breakpoint, not flow to the end without stopping.

Option C: Incorrect. Breakpoints can be conditional, so they do not always stop the process unconditionally.

Option D: Incorrect. The process will stop at the breakpoint if the 'Request Type' value equals 'New Card', not if it does not equal 'New Card'.

Conclusion:

The correct answer is A. If the 'Request Type' value equals 'New Card', then the process will stop at the breakpoint on the 'Process Request' stage.

Blue Prism Developer Documentation: Debugging and Breakpoints

Blue Prism Training Material on Conditional Breakpoints

asked 16/09/2024
Nour Algharbi
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first