Question 81 - AD01 discussion
A process contains only 4 stages. Study the following process flow.
The data item New Date is a date data item with no initial value.
The calculation stage is configured as follows:
What will happen when you execute the Create Date stage?
A.
5 days will be added to today's date and the result stored in the New Date data item.
B.
1 month will be added to today's date and the result stored in the New Date data item.
C.
1 week will be added to today's date and the result stored in the New Date data item.
D.
The process will throw an exception as the New Date data item is null.