Question 124 - AD01 discussion
Examine the following Blue Prism Process diagram:
The initial values for the 3 data items are displayed in the diagram above.
The expression in 'Decision A' is:
lnStr([City 1], 'm') > 0
The expression in 'Decision B' is:
Upper([City 2]) = 'NEWYORK OR Replace( 22/07/2020', '/'. '-') = '22-07-2020'
The expression in 'Decision C' is:
TrimEnd([City 3]) = Barcelona' AND Right([City 2],4) = 'York'
What will happen when the process flow executes?
A.
The diagram will flow through the Calculation stage named 'A'
B.
The diagram will flow through the Calculation stage named 'B'
C.
From the information available, the outcome is unknown
D.
The diagram will flow through the Calculation stage named 'C
Your answer:
0 comments
Sorted by
Leave a comment first