A process is currently scheduled to run every day but needs to be temporarily stopped for 3 months According to best practice, how should this be done?

A.
Retire the Schedule for the required period. then Unretire it
Answers
A.
Retire the Schedule for the required period. then Unretire it
B.
Clone the Schedule and set a new start date on the clone
Answers
B.
Clone the Schedule and set a new start date on the clone
C.
Set an End Date on the Schedule, then create a new Schedule to Start after 3 months
Answers
C.
Set an End Date on the Schedule, then create a new Schedule to Start after 3 months
D.
Pause the Schedule for the required period
Answers
D.
Pause the Schedule for the required period
Suggested answer: D

Explanation:

Pausing a Schedule:

Pausing the schedule is the best practice for temporarily stopping a process. This maintains the schedule's configuration and simply suspends its execution for the specified period.

Maintaining Configuration:

Pausing the schedule ensures that once the period is over, the same schedule can be resumed without needing to recreate it or adjust any start/end dates. This approach is simpler and minimizes the risk of configuration errors.

Reactivation:

After the required period, the schedule can be easily unpaused to resume its normal operation.

Blue Prism documentation on scheduling and best practices for managing schedules.

asked 16/09/2024
Adrian Chirtoc
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first