A process is currently scheduled to run every day but needs to be temporarily stopped for 3 months According to best practice, how should this be done?
A.
Retire the Schedule for the required period. then Unretire it
B.
Clone the Schedule and set a new start date on the clone
C.
Set an End Date on the Schedule, then create a new Schedule to Start after 3 months
D.
Pause the Schedule for the required period